Client
Façade contractor
Site
New waterfront residential development
Location
Shoreham-by-Sea, West Sussex
Work
Window remedials: seal replacement and minor mechanical adjustments
Team
IRATA Level 3 supervisor and Level 2 technician
Dates
31 October to 1 November 2026

The job

Windows on a new block of flats on the Shoreham waterfront needed remedial work from the outside: seals replaced and minor mechanical adjustments. The façade contractor needed a rope access team to do it over a weekend, working alongside two of their own people.

What we did

  • Wrote the RAMS and had them approved by the client before the job.
  • Set up a modular temporary deadweight anchor system on the roof, so the ropes were rigged without fixing anything into the new building.
  • Sent a two-person IRATA team: a Level 3 supervisor working on the ropes, with a Level 2 technician.
  • Worked window by window down the façade, replacing seals and making the adjustments from the ropes.
  • Worked alongside the contractor’s own team on site across the Saturday and Sunday.